View Our Products
CNC Machine Shop

We are equipped with state-of- the-art machining and special process facilities to produce parts of exceptional dimensional accuracy. The machine shop consist of Conventional, Special purpose, Semi-Automatic, CNC Machines with latest version of operating control systems.

Machine Chuk / Table
Size (mm)
Capability
(Tolerance)
Max Job
weight(Kgs)
Conventional
  • Center Lathe
  • Vertical Turret Lathe
  • Milling M/c
  • Jig Boring M/c
  • Horizontal Boring M/c
  • Bed way Grinding M/c
  • Plano Miller M/c
  • Multi Spindle Drilling M/c
  • Ø 500
  • Ø 1000
  • 1000 x 1000
  • Ø 750
  • Ø 1000
  • 5000 x 1000
  • 6000 x 2000
  • Ø 750
  • 50 mic
  • 50 mic
  • 50 mic
  • 10 mic
  • 25 mic
  • 50 mic
  • 50 mic
  • 10 mic
  • 100
  • 500
  • 10
  • 250
  • 250
  • 3000
  • 2000
  • 500
CNC
  • Vertical Machining Center
  • Horizontal Machining Center
  • Turning Center
  • Turn Mill Center
  • Gear Hobbing M/c
  • 1000 x 650 x 450
  • 800 x 800
  • Ø 400
  • Ø 500
  • Ø 900
  • 2 mic
  • 1 mic
  • 1 mic
  • 1 mic
  • 1 mic
  • 750
  • 1100
  • 25
  • 25
  • 250

The Machining processes are:
  • Turing
  • Facing
  • Boring
  • Milling
  • Drilling
  • Planning
  • Shaping
  • Grooving
  • Face Grinding
  • Cylindrical Grinding
  • Honing
  • Gear Hobbing
  • Threading
  • Lapping
  • Tapping
Our value added processes includes

  • Painting
  • Vibro Polishing
  • Tumbling
  • Belt Linishing
  • Straightening
  • Spot Welding
  • Orbital Riveting
    Heat Treatment
  • Annealing
  • Through Hardening
  • Case Carburizing
  • Case Carbonitriding
  • Tuffriding
  • Iron Nitriding
  • Induction Hardening
    Surface Treatment:
    • Phosphating
    • Chemical Impregnation
    • Zinc Plating
    • Blackening
    • Hot Chrome Plating
    • Nickel Plating
    • Silver Plating


Production Lead Time

CATEGORY AUSTRALIA CANADA UK/EUROPE US
Castings / Forgings 8 Weeks 8 Weeks 8 Weeks 8 Weeks
Machining (if Applicable) 12 Weeks 12 Weeks 12 Weeks 12 Weeks
Transit time to Warehouse 6 Weeks 5 Weeks 4 Weeks 5 Weeks